What Changed in NZS 3910:2026 and Why It Was Revised
If you’re searching for the construction contract NZS 3910:2023, you’re almost certainly after the current edition of New Zealand’s standard conditions of contract. That edition is NZS 3910:2023, which replaced the 2013 version and was published in late 2023. Standards New Zealand has not issued a separate 2026 edition, so this guide covers the 2023 revision as it applies to projects tendered and delivered in 2026.
The New Zealand Infrastructure Commission – Te Waihanga and the Construction Sector Accord commissioned the revision. A review committee drawn from government agencies and construction and infrastructure organisations was led by Standards New Zealand, as Building Disputes Tribunal explains. According to the Standards New Zealand reference guide, the aim was a contract that suits most contracts most of the time and cuts the need for special conditions. It works for anything from small building projects to multi-million-dollar infrastructure.
For quantity surveyors, contract administrators and project managers, the headline changes are:
- The Engineer’s dual role is split in two.
- Time bars and written-instruction requirements are clearer.
- Dispute resolution is simpler, with a new review step.
- A target price option now sits alongside the existing pricing methods.
- Pricing terminology has changed.
- An order of precedence clause settles conflicts between contract documents.
Each of these shapes how a project is priced, administered and reported. The sections below take them one at a time.
The Split of the Engineer Role: Contract Administrator and Independent Certifier
Under the 2013 edition, the Engineer acted as both the Principal’s agent and a fair, impartial decision-maker. The 2023 edition separates those functions. As Building Disputes Tribunal summarises, the engineer’s dual role becomes two roles: the Contract Administrator and the Independent Certifier.
In practice, the Contract Administrator acts for the Principal and handles day-to-day administration, instructions and assessments on the Principal’s behalf. The Independent Certifier stands apart and makes the impartial decisions the Engineer once made. Duncan Cotterill’s commentary describes this as the end of the "Engineer to the Contract" as a single figure.
The contract still leaves room to move. The Contract Administrator and the Independent Certifier may be the same person (clause 6.1.6), which can suit smaller projects. Where one person holds both roles, the parties need to be clear about which hat is on when making a decision. Where the roles are separated, the people appointed should know in advance who values variations, who assesses extensions of time and who certifies payment.
A related change is the review process at clause 6.4. Previously, the Engineer could effectively review its own decisions. Now a dissatisfied party has a defined route to challenge them. For commercial teams, that means documenting every assessment and certificate as though it may be reviewed.
For QS teams, the split changes the workflow. Valuations, payment assessments and variation pricing need to be prepared with the right recipient in mind. A well-structured quantity surveying report that traces each figure back to its contract basis makes it easier to support whichever role is making the call.
Variations, Time Bars, Written Instructions and Dispute Steps
The 2023 edition tightens the procedural side of change and claims. Per NZES’s explainer, the language around time bars is clearer: contractors must give notices within defined timeframes to preserve their right to claim. The same source notes that the definition of a variation and of a legitimate instruction has been tightened. Verbal instructions still happen on site, but the contract requires written confirmation.
This has direct consequences for how teams run a project:
- Notices: Diary the notice periods at the start of the contract, not when a problem lands. A late notice can sink a valid claim.
- Instructions: Confirm verbal site directions in writing straight away, noting who gave them and what they covered.
- Variations: Keep a register that ties each instruction to its pricing basis, its time impact and its status.
- Extensions of time: The revised standard encourages parties to agree variations and extensions of time wherever possible, a collaborative intent noted in commentary on the new edition.
Disputes have been restructured too. The old dispute provisions give way to a much simpler section 13. Contractor Magazine notes that it requires parties to negotiate in good faith through senior management before invoking further dispute resolution. Escalation is therefore staged. Site-level disagreement goes to the review step, then to senior management, and only after that to the formal processes.
The practical lesson: disputes are easier to resolve when the records are good. Programme updates, instruction logs, valuation workings and correspondence should all tell the same story. Teams working on both sides of the Tasman should also remember that security-of-payment regimes vary by jurisdiction. For Australian projects, our guide to the Security of Payment Act in NSW covers a different statutory framework, which shouldn’t be confused with the NZS 3910 process.
Target Price, New Terminology and Cost Planning Impacts for QS Teams
The most useful change for cost teams is the new pricing option. NZS 3910:2023 adds a target price option alongside lump sum, measure and value, and cost reimbursement. As described by Construction Law Professionals, it lets the parties share the benefit of savings or the burden of overruns when the actual price drifts from the agreed target.
For a QS, a target price arrangement shifts the emphasis from a fixed number to a managed one. The target needs a defensible basis, usually a well-developed estimate and cost plan, and cost reporting has to track actual cost against that target throughout delivery. Forecasting, risk allowances and contingency must stay visible, because movement against the target drives the gain or pain share. A cost reference such as the Rawlinsons construction cost guide can support benchmarking, though it’s only one input to a target.
The terminology has changed as well. According to Dentons’ summary of the new edition:
- "Preliminary and General" replaces "On-Site Overheads".
- "Margin" replaces "Off-Site Overheads and Profit".
- The "Interim Final Account" and "Final Account" are now defined terms.
These sound like small edits, but they affect tender documents. Schedules of prices, BOQ templates and cost-plan layouts that still carry the 2013 labels can create ambiguity when read against the new contract. Estimating teams should update their templates so the price structure matches the contract vocabulary.
Two other points matter for cost planning. First, the standard doesn’t include a risk allocation table, as the Master Builders’ good contracting guidance notes. Risk allocation must be handled deliberately in the tender documents and the cost plan, not assumed. Second, the new order of precedence clause means that when documents conflict, the listed order decides which one prevails. QS teams preparing BOQs and specifications should check how their documents rank, because an inconsistency between a BOQ and a specification can now have a defined outcome.
Our overview of quantity surveying services explains where cost planning, tendering support and contract administration sit across the project lifecycle.
Checking Version and Licence, Transitioning from 2013, and PDL’s Support
Before relying on any contract, confirm which version it’s based on. Many live contracts still use the 2013 edition, and adapted contracts can blur the picture. Standards New Zealand requires adapted contracts to carry a licence statement at the start, in the form "This contract is adapted from NZS 3910:2023 under licence from Standards New Zealand, licence number [unique number assigned on purchase]." A missing or unclear statement is a prompt to ask which text the parties actually signed.
A sensible document-control checklist for the construction contract nzs 3910:2026 enquiry looks like this:
- Confirm the edition (2013 or 2023) on the contract cover and agreement.
- Check for the licence statement on any adapted version.
- Identify the special conditions and compare them with the base text so changes are visible.
- Check the order of precedence in the contract agreement.
- Confirm the pricing option and the roles named for Contract Administrator and Independent Certifier.
Moving from 2013 is mostly a matter of updating habits. Projects already running under 2013 generally stay under that text, so teams may run both editions at once. The risk is mixing them up, for instance, applying the 2023 review process to a 2013 contract. Keep a project-level note stating the edition and the key clauses that govern notices, variations and disputes. For new tenders, update templates, notice registers and valuation formats to the 2023 wording. A formal project charter can also record the contract form, roles and reporting expectations at the outset.
Readers on Australian projects should remember that NZS 3910 is a New Zealand standard. Using it in Australia would be a contractual choice rather than a default, and no Australian equivalent has been verified for this article.
PDL Projects supports the commercial side of this work across New Zealand and Australia. Our quantity surveying, cost management, contract administration and project management services help teams turn contract clauses into practical controls: cost plans and BOQs aligned to the contract wording, variation and claim registers, valuations and final account support. We also deliver PMI certification training for professionals who want to sharpen their change, risk and governance skills. This article is general information, not legal advice, so projects with specific questions should seek advice on how the contract applies to them. Contact us today for your construction contract support: www.pldprpojtcs.com