What a Project Charter Template Must Include, and How Long It Should Be
If you’re reading this in November, you’re probably lining up projects that start once the holiday break ends, or chasing approvals before the office shuts for the year. A project charter template is the quickest way to turn a loose idea into an authorised project. It’s a formal planning document that captures scope, goals, team members, stakeholders, resource needs and timelines, as Atlassian’s project charter guide describes it. PMI puts it slightly differently: the charter formally authorises the project’s existence and gives the project manager authority to apply organisational resources to project activities.
On most construction and infrastructure work in New Zealand and Australia, a good charter covers these headings:
- Project purpose and business case: why the project exists and what problem or opportunity it addresses.
- Objectives and success measures: specific, checkable outcomes rather than general intentions.
- Scope and exclusions: what’s in, and just as importantly, what’s out.
- High-level deliverables and summary milestones: the charter sets the summary milestone schedule that later shapes detailed schedule planning.
- Budget estimate: an early cost envelope and its funding source.
- Key stakeholders, sponsor, project manager and team roles.
- Assumptions, constraints and initial risks.
- Approval authority and sign-off.
As for length, the charter is a high-level document, so shorter wins. A single page is realistic for a small fit-out or minor works project. A larger infrastructure job might need three to five pages. If yours runs past that, you’re probably writing the project plan, which is a different document (more on that distinction below).
Don’t fill every field just because a template has it. An over-detailed charter goes stale the moment the first design change lands, and people stop reading it. Keep it short enough that your sponsor actually reads it before signing.
Step-by-Step: Completing the Charter Before Year-End Project Kick-Offs
What you need before step 1:
- The business case or client brief
- Any signed agreements, letters of intent or the statement of work
- A draft list of stakeholders, including the client, sponsor, consultants and likely contractors
- Any early budget figure the sponsor already has in mind
- Notes on organisational constraints, such as procurement rules or approval thresholds
These line up closely with the PMBOK inputs for developing a charter: the statement of work, business case, agreements, enterprise environmental factors and organisational process assets.
Step 1: Confirm the sponsor and the approval path
Before you write a word, name the person who can sign. A charter without a named sponsor is a wish list. Diaries fill fast in November, so book the sign-off meeting now instead of hoping a signature turns up by email in the last week of December.
Step 2: Write the purpose and business case in plain language
Two or three sentences will do. State the problem, the proposed project and the benefit. If you can’t do that briefly, the project isn’t yet clear enough to authorise, and that’s a useful thing to find out early.
Step 3: Define scope boundaries and exclusions
List what the project delivers and what it explicitly doesn’t. On construction projects, exclusions like external works, furniture, fixtures and equipment, or council consent fees are common sources of later dispute. Writing them down early costs nothing.
Step 4: Set objectives and success measures
Use measures a third party could verify: practical completion by a stated date, a budget ceiling, a quality standard, a safety outcome. Avoid phrases like "deliver a high-quality result" unless you define what that means.
Step 5: Draft the summary milestones
Stick to the big markers: design complete, procurement complete, construction start, practical completion. Detailed programming comes later. If your kick-off is in January, remember that many New Zealand and Australian trades and consultants run at reduced capacity over the holiday period, so a realistic first milestone date matters.
Step 6: Enter a rough budget and funding source
Be upfront that this is an early estimate, not a final financial plan. The charter should say what the project is expected to cost, where the money comes from, and any additional resources needed. State the basis and the level of uncertainty.
Step 7: Record assumptions, constraints and top risks
Capture the five or six that could change the project’s direction, such as consent timing, site access, supply lead times or funding conditions. This isn’t a full risk register, just the items the sponsor should know about before approving.
Step 8: Circulate, revise and obtain sign-off
Send a draft to the sponsor and key stakeholders, collect comments in one round, then finalise. Once it’s signed, store the charter where everyone can find it. Charters often get updated as the project evolves, so record a version number and date from day one.
Linking the Charter Budget to Cost Plans, QS Estimates and BOQs
The budget line in a charter is a starting point, not a commitment to a specific price. Think of it as an envelope. Everything that follows should either fit inside it or prompt a conversation about why it doesn’t.
Here’s how the cost documents typically relate on a construction project:
- Charter budget estimate: rough, high-level figures based on the brief, comparable projects and early assumptions.
- Cost plan: a structured breakdown prepared as design develops, allocating the budget across elements such as substructure, structure, services and external works.
- Quantity surveyor’s estimate: a more detailed, measured assessment once drawings are sufficiently developed.
- Bill of Quantities (BOQ): the itemised schedule used for tendering, so contractors price the same scope on the same basis.
The discipline that matters here is traceability. If the charter gives a project cost, your first cost plan should show how that figure is allocated and what allowances and contingencies it holds. When the QS estimate lands higher or lower, you can point back to the charter assumptions and explain the gap, rather than arguing over numbers with no shared starting point.
A few habits keep the link healthy. State what the charter budget includes and excludes (professional fees, consent costs, GST treatment and escalation, for example). Record the date and basis of the estimate. Note the contingency approach. And when the cost plan moves materially, update the charter or log the change formally rather than letting two documents quietly disagree.
AI-powered cost estimation tools can help here by producing a quick benchmark against comparable projects, which is handy when the sponsor wants a number before design exists. They support the charter’s budget section, but they don’t replace a QS-prepared estimate once scope and drawings are firm. Treat the early figure as a range and say so.
Variations, Claims and Change Control in Your Charter
Construction projects change. Design gets refined, site conditions throw up surprises, clients adjust requirements. The charter can’t predict these changes, but it can set the rules for handling them, and that’s where many projects either stay in control or drift.
A charter should include a short change control statement. A typical clause says that changes to the charter will be coordinated with and approved by the signatories or their designated representatives. Extend the same principle to scope, budget and schedule: who can approve a change, up to what value, and how it’s recorded.
Useful items to include:
- Approval thresholds: for example, the project manager approves changes below a set value or time impact, and the sponsor approves anything above it.
- A change request process: a simple sequence of request, impact assessment (cost, time, quality, risk), decision and record.
- Contingency ownership: who holds contingency and who can release it.
- A reference to the contract: the charter should point to the contract’s variation and claims provisions rather than paraphrase them. Contract terms differ, and a suitably qualified professional should review them, because a charter summary is no substitute for the contract itself.
Why put this in a charter and not only in the contract? Because the charter is often the document the sponsor and senior stakeholders actually read. If it sets the expectation early that variations are priced, assessed and approved before work proceeds, you cut down on late surprises and disputed claims. It also gives the QS and contract administrator a clear mandate: assess the cost and time effect of each change, record it, and report it against the original budget envelope.
Keep this section brief. One short paragraph and a threshold table in an appendix is plenty. The aim is clarity about authority and process, not a legal treatise.
Charter vs Project Plan, and Using the Process in PMI Certification Study
The most common confusion is where the charter stops and the project plan starts. The charter authorises the project and sets direction at a high level. The project plan explains in detail how the work will be executed, monitored and controlled.
Put simply:
- The charter answers: Should this project exist, who’s in charge, and what are the boundaries?
- The project plan answers: How will we deliver it, in what sequence, with what resources, controls and communications?
The charter comes first, usually written by or with the sponsor, and it feeds the plan. Scope statements, work breakdown structures, detailed schedules, cost baselines, risk and quality plans all grow out of the charter’s high-level information. If the plan contradicts the charter, one of them needs a formal change.
For readers studying for PMI certifications, this distinction is worth mastering. Develop Project Charter is a core initiating process in the PMBOK Guide, defined as developing a document that formally authorises the project and gives the project manager authority to apply organisational resources. Exam questions often test whether you can tell charter content from plan content, and who issues the charter. If you’re building a study routine, our guide to a PMP exam prep study plan that works shows how to fit process knowledge like this into a realistic schedule, and what PMP training involves is a good starting point if you’re new to the credential. Cost-conscious readers in the region may also want the PMP certification cost breakdown for Australia and New Zealand.
A note on versions: PMI’s framework has evolved, and some third-party sources describe the charter differently under newer editions. Always check which edition your exam or employer follows against PMI’s own materials rather than relying on summaries.
If you want a ready-made starting point, several free layouts are available, including Smartsheet’s collection of project charter templates. Use any of them as a skeleton, then tailor it with the cost, contract and change control sections described above. This article is general guidance only, not legal, contractual, engineering or financial advice, so have contract terms and budgets reviewed by a qualified professional before relying on them.